docs: mark Phases 4, 5, 15, 16 done in roadmap

This commit is contained in:
michael
2026-04-27 08:42:19 -07:00
parent 7eae081dd7
commit 5668ba1f69
2 changed files with 10 additions and 9 deletions

View File

@@ -13,10 +13,11 @@ See [docs/BUILDING.md](docs/BUILDING.md).
## Status
Pre-alpha. Phases 03, 6, 7 code complete (workspace scaffold, D-Bus daemon,
storage layer, FIDO2 backend with mock+real authenticator, PAM pending-flag
backstop, `authforgectl` CLI). Phase 4+5 (policy apply via pam-auth-update +
lockout simulator) is next. See [docs/plans/](docs/plans/) for design,
roadmap, and per-phase implementation plans.
Pre-alpha. Phases 07, 15, 16 code complete (workspace scaffold, D-Bus daemon,
storage layer, FIDO2 backend, policy apply via pam-auth-update with lockout
simulation, PAM pending-flag backstop, `authforgectl` CLI, `gnome-control-center`
overlay, Ansible role for fleet deployment). Phase 8 (GUI Security Keys tab) and
Phase 12 (recovery flow) are the next single-lane bundles. See [docs/plans/](docs/plans/)
for design, roadmap, and per-phase implementation plans.
Copyright 2026 Dangerous Things, LLC. Licensed under the Apache License, Version 2.0.