docs: mark Phases 3, 6, 7 done in roadmap

This commit is contained in:
michael
2026-04-27 08:30:09 -07:00
parent 22938f657a
commit 865e37b6aa
2 changed files with 10 additions and 9 deletions

View File

@@ -13,9 +13,10 @@ See [docs/BUILDING.md](docs/BUILDING.md).
## Status
Pre-alpha. Phases 02 code complete (workspace scaffold, D-Bus daemon, storage
layer with policy.d / pending / credentials / userdb); Phase 3 (FIDO2 enrollment
backend) is next. See [docs/plans/](docs/plans/) for design, roadmap, and
per-phase implementation plans.
Pre-alpha. Phases 03, 6, 7 code complete (workspace scaffold, D-Bus daemon,
storage layer, FIDO2 backend with mock+real authenticator, PAM pending-flag
backstop, `authforgectl` CLI). Phase 4+5 (policy apply via pam-auth-update +
lockout simulator) is next. See [docs/plans/](docs/plans/) for design,
roadmap, and per-phase implementation plans.
Copyright 2026 Dangerous Things, LLC. Licensed under the Apache License, Version 2.0.